[BC Construction Association] BCCA
HOME

Accreditation

Advertise

Bid Depository

Contact the BCCA

COCA

EUSTEP

Green Buildings

Group Benefit Plan

Industry Events

Industry Links

ISTEP

Job Postings

Join Us

News and Events

Online Directory

Planroom

Policies

Reports / Publications

Resources

Standard Documents

Step for Women

Survey

Who's Who

Tundra
Official Truck
of the BCCA



BCCA email:
bcca@bccassn.com

BCCA
210 - 174 WILSON ST.
VICTORIA, BC  V9A 7N6

PHONE: 250-475-1077
FAX: 250-475-1078


[BCCA Advertisement]

policies Home
CONSTRUCTION CONTRACT ADMINISTRATION


Deficiencies
Where there are deficiencies, the consultant should provide the contractor with a complete and concise list to enable completion by a mutually accepted date. Funds held back for deficiencies should be based on the value of the outstanding work and should not exceed two times said value.

Markups To Changes Of The Work
BCCA endorses the standard markups for Overhead and Profit for changes to the work as defined in CCA16 Guidelines For Determining The Costs Associated With Performing Changes In The Work; 20% on the GC's own work and 15% on the trade contractors work.
[Return to Policies]   [Top]



HOME
[]


CLICK HERE to take the BCCA - HUMAN RESOURCES SURVEY


Use of this website is subject to the following Disclaimers.

HOME | Accreditation | Bid Depository | Calendar | COCA | Contact Us | News | Industry Links
Online Directory | Planrooms | Policies | Reports/Publications | Resources | Standard Documents | Who's Who


© 1996-2007 British Columbia Construction Association